Broward County WTP 1A & 2A Treatment Unit #2 Rehabilitation

05/30/19 to Present 90% Complete

Contract Amount $ 1,913,010

Rehabilitation of two (2) Existing Lime Treatment Units at Broward County's Water Treatment Plant 1A & 2A. This work Rehabilitation of two (2) Existing Lime Treatment Units at Broward County's Water Treatment Plant 1A & 2A. For each of the two units the work included the removal and replacement of the existing outer draft tube, impeller drive shaft, and complete interior eco-blasting and re-coating of one unit; as well as replacement of the existing collection, effluent and radial launders with new 304 Stainless Steel launders.

Broward County WTP 1A & 2A Treatment Unit #2 Rehabilitation Broward County: Projects